1/16/2012
19
First Cast of the Day
• W
et the conductivity cell in accordance with
Application Note 2D, approximately 1 hour before
the cast.
• Before taking the first cast:
– Verify all cables and dummy plugs are installed.
– Verify all plumbing is properly connected.
– Remember to remove the soaker tube from the conductivity
cell, covers from PAR sensors, pH bottles, etc.
• Making a checklist that includes all sensors in your
configuration
can help prevent things from being overlooked.